SBB Marshalling Yard Limmat Valley
Client: |
Schweizerische Bundesbahnen |
Location: |
Limmat Valley, Switzerland |
Construction period: |
05/2018 - 07/2018 |
Executing companies: |
Sersa Group AG (Schweiz), Sersa Technik AG, |
Project Description
Partial project 1:
In the area between approx. 13,650km to 13,750km and points 381, 382, 383 and 384, as well as parts of tracks 681-688 will be renewed. Ballast cleaning will be carried out. In addition to the renewal of the track, works on the banquet, cable duct, catenary, and safety installations are carried out as well.
Partial project 2:
In the area between approx. 14,000km to 14,170km points 501, 501/K6 (middle section), 502, 503, 504, 505 and 531, as well as part of track 294 are renewed. The ballast will be cleaned during this work. In addition to track renewal, works on the banquet, cable duct, catenary, and the safety installations are carried out as well.
Partial project 3:
In the area between approx. 14.695km to 14.810km track 174 will be renewed. Ballast cleaning will be carried out. In addition to the renewal of the track, work is also to be carried out on the banquet, cable duct, overhead contact line, level crossings and the safety installations.
Features
- Several intensive construction phases at weekends
- 3-shift operation
- Contractor will provide a complete logistics service
- Contractor is responsible for safety
Building under operation
Preparatory and finishing work was carried out during operational hours. The main work was carried out in intensive building phases at the weekends.
Technical Data
Number of switches: |
12 pieces |
Length of switch meters: |
1 615m |
Length of feeder track: |
529m |
Rail demolition: |
1164m |
Sleeper demolition: |
1551 pieces |
Track panel demolition: |
308t |
Excavation: |
1146t |
Ballast installation: |
1231t |